Lam Research

CDA Dryer Replacement

Client: Lam Research

Estimation: $75,000

Duration: 5 months

ADC Construction Management was contracted by Lam Research for preconstruction and construction services for the CDA Dryer Replacement Project. The project was performed in an operating facility and any impact or shutdown to fab or ongoing operations was unacceptable. ADCCM was responsible for layout new piping and placement of new air dryers. New temporary air dryers were needed to be tested and introduced into the existing system during removal and replacement. The project also included pressure testing piping, labeling all piping, duct and conduit to indicate commodity and direction of flow and seismic anchoring of new air dryers.

ADCCM completed the project on schedule without disruption to the existing operations.